Column Internals Installation
Column internals that require welding, such as packing supports, liquid collectors, gas-liquid distributors, etc., should preferably be completed before packing installation to prevent weld slag from entering the packing and causing a fire.
The oil layer on the surface of metal packing can easily catch fire under the high temperature conditions of weld slag, and plastic packing is even more prone to fire. Weld slag left in the column can also cause blockage of the liquid distributor and affect column efficiency.
If some components must be installed during or after packing installation, asbestos cloth or asbestos sheet should be laid below the welding to isolate it from the packing.
Correct Installation Steps:
- Install the packing supports.
- Install the packing.
- Install the packing fixing or hold down device and adjust it to the horizontal.
- Install the liquid distributor or redistributor, fix it, and adjust it to the horizontal.
- After installation, check it thoroughly.
Packed columns that cannot reach the design indicators collectively referred to as failure. In the packed column operation, sometimes failure may caused due to one or more factors. Here we summarize some common fault diagnosis and treatment methods to ensure the efficient operation of the equipment.